Frontier Economics : Report No. 2 December 2024

The Frontier Economics report can be found at: https://www.frontier-economics.com.au/wpcontent/uploads/2024/12/Report-2-Nuclear-power-analysis-Final-STC.pdf

Pricing of the National Electricity Network (NEM) AEMO base cases are significantly more expensive than an alternative with 38% nuclear energy and 54% renewables. Refer to Tables 9 and 10 of Frontier Economics, Report No.2, Dec 2024. 

Table 9 – Generation, network and total system costs – sum real $ billion (2025-2051)

Scenario Generating Cost ($billions)Transmission Cost ($billions)Total Cost($billions)
Step Change AEMO base case$528$66$594
   Nuclear alternative$402$44$446
Progressive AEMO base case$405$32$437
   Nuclear alternative$317$14$331

Table 10 – Generation, network and total system costs – NPV  $ billion (2025-2051)

Scenario Generating Cost ($billions)Transmission Cost ($billions)Total Cost($billions)
Step Change AEMO base case$190$35$225
   Nuclear alternative$142$21$163
Progressive AEMO base case$148$17$166
   Nuclear alternative$116$8$124

Several critical factors were overlooked in CSIRO in GenCost 2024:

  • For intermittent renewables around three times the generating capacity is needed to match baseload energy from coal or nuclear power stations.
  • A renewables grid is far bigger than a grid with nuclear electricity connected into it, particularly where transmission lines already exist.
  • Renewables + firming took a single point in time firming requirement, rather than consider how firming works within the AEMO ISP model.

Discover more from C2N Australia

Subscribe now to keep reading and get access to the full archive.

Continue reading